Saturday, October 27, 2007

Locking Up

We are now at the point where we're locking up the house. Last week the wood floors were put in -- in one day! They are not the pre-finished type, so they will be sanded and stained on-site just before the house is ready to move in to. Little white hexagon tiles (3/4") are being laid in the bathrooms and laundry room, and I'm really excited about those. They are very "period." Our master shower is also being crafted with 3x6-inch white subway tiles (see photo), and eventually our kitchen backsplash will have those too.

On the outside of the house, trenches are being dug and utility lines are being laid. Unfortunately this past week has been a bit of a wash on that, though, because it's been raining almost the whole week. The good news on the rain is that our creek now has a bit of water in it again!

The most noticeable addition to the exterior, besides the siding being finished, is the garage doors. The style of the garage door panels and windows coordinates with our front door (would you expect anything less?). The three-lite pattern of the window panes also coordinates with the windows on the house. The white parts of the garage doors will be painted green to match the siding. I believe the painter is supposed to be back soon to paint the rest of the exterior.

Another addition to the outside of the house is the back deck. We were planning to add that on down the road, but because the back yard is such a slope, and because we'd have to build some sort of steps off the back door anyway, we decided to go ahead and do it. In the photo, you can see that surrounding the deck is trees that have just started turning colors for fall.

Last night we hosted the monthly Young family (my mom's side) poker game for the last time at the rental house. Several people met me beforehand at the new house for a pre-game tour. The first comment from my grandpa, ever the cynic, was, "How many people are going to live in this house? Forty-seven?" Gotta love him. :)

Jason, Mike (Jason's brother/cabinet guy) and Allen (Jason's step-dad) are busily installing the cabinets in the kitchen, master bathroom and upstairs bathroom this weekend. We'll try to get a blog entry up showing the cabinets by early next week.

Sunday, October 7, 2007

Siding is going up

The same Amish crew that did our framing is now installing the siding and exterior wall trim. In the photo, you can see the green siding on the house and the cedar shingles in the gables.

On the inside, drywall was installed, mudded and sanded. It's amazing how much bigger the rooms look now that they are defined by walls. The painters took a first pass at the inside, priming the walls and ceilings. The primer was tinted to match the colors we chose for the walls, which is nice because we have a preview of the painted walls before we are committed. There is just one color we might tweak, which is the one that will be in all the main rooms on the first and second floors. (Does anyone besides me know the difference between brownish-gray and grayish-brown?)

The front door was installed late this week. It is very much Craftsman-style, with the divided lights at the top, the dentil "drip mold" ledge, and the vertical panels at the bottom. It will eventually be stained a medium brown color.

Because our lot is so sloped, we had to bring in loads of dirt to fill in around the house and to help direct the flow of water from the field uphill from our lot, so that it doesn't run right toward the house.

Lastly, kudos to Jason and his dad for sweating it out yesterday (literally -- it was 92 degrees on Oct.6!) to saw down a 40"-45" wide tree that had been hit by lightning and had become an eyesore. They also cleared out some brush out by the street to make room for our mailbox.

Coming attractions: Installing the unfinished hardwood floors and the tile in the bathrooms and laundry room.

Saturday, September 22, 2007

Brickers, Insulators, Drywallers, and Septic


I've been reluctant to post any new pictures of the front facade of the house, mostly because the "front yard" is a junk pile. However, I'm so thrilled with our Craftsman-style brick piers (i.e. columns) that I had to snap a photo. The Amish masons did a fantastic job, and they are fast!! They bricked the entire skirt, the chimney (wow, what a ton of bricks!), and the piers in just a little over a week.

The initial insulation has also been completed this week. Hollie and I chose to go with foam insulation that gets blown in over traditional fiberglass insulation. The upfront costs are a little higher, but everyone (and I mean everyone -- even the plumber!) says this will be the best long-term investment we could have made over the life of the house. The insulator estimated our monthly utility bill at $60 or less.

The insulation installation process (say that 5 times fast) is pretty interesting. After initial sealing of the windows and other small cracks, the foam is blown in with a long tube from the truck. It then expands and fills in all possible voids within the walls and/or rafters. After the drying process, the guys come back with a large tool that scrapes the walls smooth so that the drywall attaches over the studs.

We should have drywall hung by early next week, at the latest. I expect that to have a huge impact, as rooms will be defined three-dimensionally for the first time. That is huge for me, as I think I was born without a right brain (that's right as in direction not as in sanity :) ).

And the dirtiest job of the week goes to Jerry, the guy who dug into bedrock to gingerly place two concrete tanks underground for the septic system. He also installed the lateral field in a...well, field...that sits just above the house. I can't see any of it of course, because he worked so fast it was all buried before I got there. I guess I'll have to take his word that it's all done. If it's not, I think we'll know pretty quickly. :)

Thursday, September 13, 2007

All Stacked Up

The Amish masons are the newest crew at the house. So far they've completed the retaining wall, the basement walkout, and they're two-thirds of the way up the chimney. If you've seen our house on the lot, you know how high off the ground the top of the chimney is. If you haven't, it's over three stories up because it's on the walkout side of the house, and it extends up even with the peak of our highest roofline. Let's just say we're glad they're not afraid to climb the scaffolding and balance up there for hours on end while placing bricks and mortar!

We chose the brick several months ago after reviewing samples the size of a placemat. Luckily we picked out a winner! Our brick is the Catawba Vista design by Hanson Brick, which has a mix of several muted colors. It's made to look old, because the edges are rough and the surface has bumps, rather than a smooth, even finish. We also chose buff mortar instead of the standard gray, because buff is more "period." I don't think anyone could say that Jason or I pick anything on a whim -- everything is chosen for a specific reason!


Other happenings around the house: shingles on the roof, a newly-poured concrete garage floor and the first steps toward insulation.

Coming up: expert masonry skills will be used to create our tapered porch columns. We can't wait -- those columns will really define the look of the front of the house.

Wednesday, August 29, 2007

Electricians and plumbers and painters! Oh, my!


There has been a lot of action going on at the house the past couple of weeks. Now we have electricians, plumbers, heating & air guys, painters, fireplace installers, and our trusty cabinet guy (Jason's brother Mike, my biggest fan) working around each other and the Amish framing crew.

The electricians are putting in all the boxes and wiring for lights, ceiling fans, power outlets, cable outlets, wall switches, etc. The plumbers have rouged in the baths, run PVC pipes through the house, laid the shower liner in our master shower, and installed Zachary's tub/shower. The heating & air guys have cut lots of holes in the floors and the wall joists to run their ducts, air vents and return vents. The painters have painted all the exterior trim, which includes the the trim pieces around the windows, the beadboard and molding under the eaves, the exposed rafter tails, and the decorative brackets that attach to the eaves. (In the photo, you can see our upstairs front gable with the painted trim and brackets.) The fireplace installers just came today to put in our direct vent gas unit. And last, but certainly not least, Mike drew in where the cabinets will sit in the kitchen and bathrooms so the other guys would know where to, or not to, put pipes and wires.

It's been a circus, but it's great to see things moving along and to see more people working on the house than the framers, who have been there for months (no offense, guys!). I think our electrician and heating & air guy almost came to blows today fighting over space in the wall by the front door, but the heat (highs of 90 to over 100 degrees for most, if not all, of August) probably slowed them down. It's been brutally hot, and I'm surprised anyone can stand to work on our house in this heat. It makes Jason and me very grateful for our cushy air-conditioned work places.

Stairway to ... well, you know


It was the bane of our existence a couple weeks back, but it's been settled now and we're moving on ... but we have not forgotten. What am I babbling on about, you say? Well, we had to compromise our original stairway layout, and we're not very happy about it.

Somehow the way the drafter drew it in the plans did not fit in the allotted space in real life. (Apparently this is not an uncommon occurrence in home construction -- right, Mike and Michelle?) Basically, we needed room for two more stairs up to the second floor, to get the angle we needed to fit within code and to provide enough headroom for the basement door and basement steps.

There was supposed to be a landing on the main floor, with the stairway to one side, a wall across, and open on the other facing sides (see photo). The landing was supposed to serve as a walkway to get from the hallway outside our master bedroom to hallway servicing the dining area, laundry area and garage. Unfortunately, by the time the framers figured out it couldn't be built as it was drawn by our drafter, the wall facing the stairway could not be moved out to accommodate the extra needed space, because it is a load-bearing wall, holding up the main support beam down the middle of the house.

So we had to change our plans and move the landing up higher, add a step to one side, and we'll have to add a railing to the other side. We'll no longer be able to use it as a walkway, which is a bummer, because that was a neat, and unique, feature of the house. Believe me when I say we tried everything to avoid making the change! Now, nobody else would ever know that there's anything "wrong," but we will always know ....

Friday, August 10, 2007

We have windows!


That's what I squealed in Jason's ear yesterday afternoon when he answered his cell phone. What a difference the addition of color makes to the exterior of the house! I can't wait to see how the burgundy windows will pop against the green (Dried Thyme from Sherwin-Williams) siding. In case you are interested, the windows are from Semco, double-hung clad with simulated divided lights -- three over one -- in Vintage Burgundy. We just chose our exterior trim color today, which is Rockport Gray, one of the Pottery Barn colors from Benjamin Moore (Spring 2007) . Mark asked me for the trim color earlier in the week, which caught me off guard since we don't even have any trim up yet. He said we can go ahead and paint the rafter tails and the beadboard on the underside of the rafters. The siding is on order, and the brick for the skirt and chimney is supposed to be coming soon.

By the way, this is my first blog entry ever. Jason has been nagging me for a while to do one, but I told him I like his witty comments just fine. Finally the windows inspired me enough to do it. Be sure to leave me some comments so I'll be motivated to post again!